Connection with the Olbia Airport

Connection with the Olbia Airport

The project involves the construction of a non-electrified single-track line approximately 3.4 km long, which will start from the existing line near the Olbia Terranova station and run to Costa Smeralda Airport, where a new station will be built, connected to the airport terminal via a dedicated footpath.

The project also includes the construction of a single-track link to enable connections from the new airport station towards Chilivani as well.

Electrification of the line is planned as part of another investment project.

The project to build a rail link to Olbia Airport is fully funded, including through NRRP funds.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

Advantages

  • The project will serve both traffic flows to and from the airport and regular journeys within the area comprising the municipalities of Olbia and Golfo Aranci.
  • Rail-air intermodality and improved access to rail services.
100 km/h maximum speed
4 total kilometres
231 mln € in investments

Work progress status

Below are the details of the work progress for Connection with the Olbia Airport.
  • Design
    2022
  • Permits
    2023
  • Tenders
    2023
  • Start of work
    2024
  • End of work
    2026

Connection with the Olbia Airport - Connection with the Olbia Airport

Stages of progression: WORKS

  • Design end date: 2022
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Start date of executive design and implementation: 2024
  • Work end date: 2026
  • Activation date: 2026