Development of the Orte-Falconara

Development of the Orte-Falconara

The project aims to improve passenger connections between the Tyrrhenian and Adriatic regions and to establish an alternative freight route for north-south connections. The works, carried out in several phases, mainly involve doubling certain track sections as variants along the Orte–Falconara Apennine crossing.

The project has received partial public funding, including NRRP funds.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners. 

The advantages

  • Once the works are complete, it will be possible to achieve a reduction in journey times between Rome and Ancona of up to approximately 30 minutes for some services, and between Rome and Perugia of up to approximately 15 minutes, depending on the operating schedule and the completion of the two-track expansion of the Spoleto–Terni line.
  • Improved regularity thanks to a revised operating schedule resulting from the new infrastructure configuration and the revised service schedule, partly due to the completion of the two-track expansion between Spoleto and Terni.
  • Increased capacity: from 4 to 10 trains per hour on the sections where the track has been doubled (from 4 trains per hour in both directions to 10 trains per hour in each direction).
  • Improved service accessibility.
  • Upgrades to enable the passage of freight trains.
av
200 km/h maximum speed
163 total kilometres
6,050 mld € in investments

Work progress status

  • Design
    Since 2008
  • Permits
    Since 2011
  • Tenders
    Since 2013
  • Start of work
    Since 2015
  • End of work
    Since 2025

Doubling Terni - Spoleto - Doubling Terni - Spoleto

Stages of progression: DESIGN

  • End date of the design: 2024
  • End date of the authorisation process: 2025

Strengthening Orte-Falconara - Doubling Spoleto – Campello

Stages of progression: WORKS 

  • Design end date: 1999*
  • End date of the authorisation process: 2000*
  • Date of tender publication: 2018*
  • Start date of executive design and implementation: 2020
  • Work end date: 2024
  • Activation date: since september 2024

 

* It should be noted that over the years, there have been contractual rescissions that have distended and reshaped the operations  

Orte-Falconara: Doubling Spoleto – Campello - Doubling Spoleto – Campello: SSE Spoleto

Stages of progression: WORKS

  • Start date of executive design and implementation: 2020
  • Work end date: 2025
  • Activation date: 2025

Doubling Foligno-Fabriano - Doubling Foligno-Fabriano

Stages of progression: DESIGN

Doubling PM228 - Castelplanio with by-pass di Albacina - Lot 1 PM228-Genga

Stages of progression: DESIGN

  • Design end date: 2024
  • End date of the authorisation process: 2027

Doubling PM228 - Castelplanio with by-pass di Albacina - Lot 2 Genga-Serra S.Quirico

Stages of progression: WORKS

  • Design end date: 2021
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Start date of executive design and implementation: 2023
  • Work end date: 2026
  • Activation date: 2026

Doubling PM228 - Castelplanio with by-pass di Albacina - Lot 3 Serra S. Quirico-Castelplanio

Stages of progression: PERMITS

  • Design end date: 2023
  • End date of the authorisation process: 2025

Acceleration Orte-Falconara line - Acceleration Orte-Falconara line

Stages of progression: TENDERS

  • Design end date: 2023
  • Date of tender publication: 2024
  • Start date of executive design and implementation: 2025
  • Work end date: 2026
  • Activation date: 2026

Doubling PM228 - Albacina - Doubling PM228 - Albacina

Stages of progression: WORKS 

  • Design end date: 2021
  • End date of the authorisation process: 2024
  • Date of tender publication: 2024
  • Start date of executive design and implementation: 2024
  • Work end date: 2026
  • Activation date: 2026

Falconara Junction variant: SP01 - Falconara Junction variant: SP01 - Falconara Junction 1st phase (Falconara variant)

Stages of progression: WORKS 

  • Work end date: 2026
  • Activation date: 2026

Falconara Junction variant: SP04 - Falconara Junction variant: SP04: Falconara Junction - Montemarciano - 2nd phase

Stages of progression: PERMITS

  • Design end date: 2023
  • End date of the authorisation process: 2025

Doubling Montecarotto Castelplanio - Doubling Montecarotto Castelplanio

Stages of progression: ACTIVATION

Doubling Fabriano PM 228 - Doubling Fabriano PM 228

Stages of progression: ACTIVATION