Rome-Pescara line

Rome-Pescara line

The project involves significant infrastructure and technological upgrades along the Rome–Pescara line, divided into several phases and aimed at improving transport links between Lazio and Abruzzo. The works to double the track, increase the speed and upgrade the line will reduce journey times from the current 3 hours and 20 minutes to around 2 hours.

The project has received partial public funding.

Aldo Isi was appointed Extraordinary Government Commissioner for the completion of the works.

Advantages

  • Reduced journey times: Rome to Pescara in around 2 hours, compared with the current 3 hours 20 minutes, with journey times reduced by up to 80 minutes (once the entire project is complete).
  • Increased capacity: from 4 to 10 trains per hour on the sections where the track has been doubled, with the possibility of introducing metro-type services between Chieti and Pescara.
  • Improvements to the speed and regularity of services between Pescara and L'Aquila, thanks in part to other works currently underway and planned along the L'Aquila–Sulmona line (Sulmona Bypass, new Sulmona S.Rufina stop).
  • Upgraded capacity (gauge and weight limits) to facilitate the growth of freight traffic.
  • Improved connectivity at Abruzzo International Airport, thanks to the opening of the Pescara Airport station, ensuring an intermodal connection with trains.
  • Improved traffic flow thanks to the removal of the level crossing and the elimination of traffic disruptions

 

av
200 km/h Maximum speed
52 total kilometres
16,017 mld € in investments

Work progress status

Following are the details of the progress of works on the Rome-Pescara line.
  • Design
    Since 2019
  • Permits
    Since 2020
  • Tenders
    Since 2020
  • Start of works
    Since 2021
  • End of works
    Since 2024

Bretella railway link for Sulmona - Bretella railway link for Sulmona

Stages of progression: WORKS 

  • Design end date: 2019
  • End date of the authorisation process: 2020
  • Date of tender publication: 2020
  • Start date of executive design and implementation: 2021
  • Work end date: 2024
  • Activation date: December 2025

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 0 - C onstruction III tracks Pescara PN - Pescara C.le

Stages of progression: DESIGN

  • Design end date: 2024
  • End date of the authorisation process: 2025

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 1 - Pescara PN - San Giovanni Teatino

Stages of progression: PERMITS 

  • Design end date: 2024
  • Activation date: June 2025

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 2 - San Giovanni Teatino - Chieti

Stages of progression: PERMITS 

  • Design end date: 2024
  • Activation date: May 2025

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 3 - Chieti - D’Abruzzo Interport

Stages of progression: PERMITS 

  • Design end date: 2024
  • Activation date: August 2025

Doubling of Pescara - Chieti - D’Abruzzo Interport - Lot 4 - PRG and ACC for Chieti

Stages of progression: DESIGN 

  • Design end date: 2024

Strengthening Roma - Pescara - Lot 1 - D’Abruzzo Interport - Manoppello

Stages of progression: WORKS

Design end date: 2021

  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Start date of executive design and implementation: 2024
  • Work end date: 2026
  • Activation date: 2026

Strengthening Roma - Pescara - Lot 2 - Manoppello - Scafa

Stages of progression: WORKS

  • Design end date: 2021
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Start date of executive design and implementation: 2024
  • Work end date: 2026
  • Activation date: 2026

Strengthening Roma - Pescara - Lot 3 - Sulmona - Pratola Peligna

Stages of progression: PERMITS 

  • Design end date: 2024
  • End date of the authorisation process: 2025

Strengthening Roma - Pescara - Lot 4 - Tagliacozzo - Avezzano

Stages of progression: PERMITS

  • Design end date: 2024
  • End date of the authorisation process: 2025

Roma Mandela Tagliacozzo - Roma Mandela Tagliacozzo

Stages of progression: DESIGN

Avezzano - Sulmona e Pratola Peligna - Scafa - Avezzano - Sulmona e Pratola Peligna - Scafa

Stages of progression: DESIGN