Restoration of the Palermo-Trapani via Milo line

Restoration of the Palermo-Trapani via Milo line

The project involves the restoration of the direct link between Palermo and Trapani via Milo, which was closed in 2013 due to widespread deterioration that could no longer be remedied through maintenance work.

More specifically, the interventions involve:  infrastructure improvements through modifications to the road surface and civil engineering works, adaptation to new technological standards, and the acceleration of traffic flow on diversion routes at major junctions.

Plans also include the electrification of the entire line and the construction of an underpass within the municipality of Trapani, which will enable the removal of three level crossings. The project will enable the Palermo–Trapani connection to be reopened, ensuring improved network performance and faster interconnections.

The Palermo–Trapani line via Milo is fully funded, including through NRRP funds.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

The dvantages

  • The current journey time on the Piraineto–Trapani section is 2 hours and 50 minutes (via Castelvetrano). The aim of the project is to reduce it by up to 70 minutes (via Milo).
  •  The completion of the two-track expansion of the Palermo Link will enable the development of a direct, fully-electrified service between Palermo and Trapani.
100 km/h maximum speed
47 total kilometres
323 mln € in investments

Work progress status

  • Design
    Since 2019
  • Permits
    Since 2021
  • Tenders
    Since 2021
  • Start of work
    Since 2022
  • End of work
    Since 2026

Electrification of the Palermo-Trapani via Milo - Electrification of the Palermo-Trapani via Milo

Stages of progression: WORKS

  • Design end date: 2019
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Work end date: since 2026
  • Activation date: since 2026

Restoration of the Palermo-Trapani via Milo - Restoration of the Palermo-Trapani via Milo line

Stages of progression: WORKS 

  • Design end date: 2020
  • End date of the authorisation process: 2021
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2026
  • Activation date: since 2026

Construction of a road subway of Trapani - Restoration of the Palermo-Trapani via Milo: construction of a road subway of Trapani

Stages of progression: WORKS 

  • Design end date: 2020
  • End date of the authorisation process: 2021
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2025
  • Activation date: since december 2025