Ponte San Pietro-Bergamo-Montello

Ponte San Pietro-Bergamo-Montello

The project involves the phased two-track expansion of the Ponte San Pietro–Bergamo–Montello line.

The Ponte S. Pietro – Bergamo – Montello project has received partial public funding, including through NRRP funds.

Aldo Isi was appointed Extraordinary Government Commissioner for the completion of the works.

The project stretches for approximately 19 km between the Ponte S. Pietro and Montello stations, after Bergamo. The first phase involves the doubling of the line between Ponte San Pietro and Bergamo, and includes modifications to the Ponte San Pietro station and the integration of Bergamo and Ponte San Pietro into the ACC-M.

The second phase involves the doubling of the Bergamo–Montello section with a new ACC in Bergamo, the removal of all level crossings along the line, and the construction of the necessary replacement infrastructure. The works at Bergamo station will be integrated with the project for the new rail link to Orio al Serio Airport.

Advantages

  • the expansion of services within the Bergamo junction;
  • the increase in the theoretical capacity of the section being doubled from the current 4 trains per hour to 10 trains per hour in both directions;
  • improved flow and traffic safety by removing level crossings;
  • a potential reduction in journey times.
100 km/h maximum speed
19 total kilometres
615 mln € in investments

Work progress status

Below are the details of the work progress for the Completion of the Ponte San Pietro-Bergamo-Montello line.
  • Design
    Since 2020
  • Permits
    Since 2022
  • Tenders
    Since 2022
  • Start of work
    Since 2023
  • End of works
    Since 2026

Doubling Ponte S Pietro-Bergamo - Doubling Ponte S Pietro-Bergamo

Stages of progression: WORKS

  • Design end date: 2020
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Activation Date: 2026

Doubling Bergamo-Montello - Doubling Bergamo-Montello

Stages of progression: DESIGN

Design end date: 2023

End date of the authorisation process: 2025