Palermo Ring Railway

Palermo Ring Railway

The intervention involves two operational phases, i.e. the extension of the existing single-track Palermo Notarbartolo-Giachery line to the new Politeama station, followed by the closure of the Ring from the Politeama station to the Palermo Notarbartolo station.

The first phase will also involve the construction of two stops: Libertà (scheduled to open in 2024) and Porto, located respectively on the section currently in operation and on the new port section.

Phase two includes the construction of the new Turrisi Colonna stop and the transformation of the Politeama station into a stop.

The Palermo Railway Ring project has received partial public funding.

“With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.”

I vantaggi

  • Potential for new metro-type services at the new Libertà, Porto, Politeama and Turrisi Colonna stops
  • Improved service regularity
  • Improved access to rail services
85 km/h maximum speed
2 total kilometres
142 mln € in investments

Work progress status

Following are the details of the progress of works on Palermo Ring Railway.
  • Design
    2020
  • Permits
    2023
  • Tenders
    2023
  • Start of work
    2024
  • End of work
    2028

Palermo ring railway - Palermo ring railway

Stages of progression: TENDERS 

  • Design end date: 2020
  • End date of the authorisation process: 2023
  • Date of tender publication: 2023
  • Activation Date: May 2028