Milano Rogoredo-Pavia

Milano Rogoredo-Pavia

The project involves a four-track expansion of the line between Milan Rogoredo and Pavia through the construction of a new pair of tracks alongside the existing ones, covering a total length of approximately 29 km. There are also plans to convert the service locations along the line into stops, with the exception of the Pieve Emanuele facility, which will be converted into a station.

The project is divided into two phases: the first phase involves expanding the line to four tracks along the Milan Rogoredo–Pieve Emanuele section (approximately 11 km), whilst the second phase involves extending the line to Pavia (approximately 18 km).

The project will increase capacity and enable the separation of different types of traffic, thereby specialising the two lines. At the same time, plans are in place to introduce a new suburban service to and from Pieve Emanuele.

The Milan Rogoredo – Pavia project has received partial public funding, including through NRRP funds.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

Advantages

  • a potential increase in capacity from the current 10 trains per hour to 20 trains per hour across both lines;
  •  improved service regularity by specialising traffic on the two lines.
acav
180 km/h maximum speed
29 total kilometres
987 mln € in investments

Work progress status

  • Design
    Since 2018
  • Permits
    Since 2022
  • Tenders
    Since 2022
  • Start of work
    Dal 2023
  • End of work
    Since 2026

Milano Rogoredo – Pavia - Milano Rogoredo – Pavia

Stages of progression: WORKS 

  • Design end date: 2018
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Start date of executive design and construction: 2023
  • Activation Date: since december  2026 by steps