<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=490038435288789&amp;ev=PageView&amp;noscript=1">

Milan - Venice route. Pioltello - Treviglio line. Adda Shunting Yard overpass

Milan - Venice route. Pioltello - Treviglio line. Adda Shunting Yard overpass

The area covered by the project is located along the Milan – Venice railway route, on the Pioltello – Treviglio line, in the central-southern part of the Lombardy Region, within the municipalities of Cassano d’Adda – part of the Metropolitan City of Milan – Casirate d’Adda and Treviglio, in the Bergamo province.

The following lines converge at the Adda Shunting Yard:

  1. Venice – Milan – Milan Bergamo Slow Line (hereinafter referred to as LL)
  2. Milan – Brescia High-Speed/High-Capacity Interconnection Line (hereinafter referred to as DD)

The current infrastructure configuration does not allow for a clear separation of traffic flows based on speed:

  • The LL line may only be used by suburban trains
  • The DD line can be used by High-Speed, regional and freight trains.

This results in significant differences in speed, as the DD line carries trains travelling at speeds of up to 245 km/h (once the speed-enhancement works currently under way will be completed), fast regional trains travelling at up to 160 km/h, and freight trains travelling at 100 km/h.

Furthermore, the DD Line Improvement Plan indicates that the line’s punctuality falls below the regional average.

Capacity analysis shows that daily utilisation is close to 60%, i.e. approaching the capacity limit, with full capacity utilisation at certain times of the day. 

Given that the Brescia – Verona – Padua High-Speed/High-Capacity line is already operating at full capacity, High-Speed and freight traffic volumes may only be met by carefully coordinating the train paths.

With this in mind, the new project will address the aforementioned issues and enhance the capacity of the Adda Shunting Yard, while improving punctuality. An overpass will be built near the Adda Shunting Yard to prevent the Milan – Bergamo flows along the DD from interfering with LL trains.

Under Law 52 of 7 August 2026, RFI S.p.A. Chief Executive Officer was appointed Extraordinary Commissioner for the project concerning the Milan – Venice Route. Pioltello – Treviglio line. Adda Shunting Yard overpass.

The Extraordinary Commissioner, by Order 13 of 25 September 2026, appointed Rosa Pannetta, Head of RFI SpA’s North-West Investment Department, as Sub-Commissioner.

The advantages

Some of the main benefits expected once the route will be open include:

  • No more service disruption at the Adda Shunting Yard, with enhanced timetable planning and service regularity;
  • Creating the conditions for any further traffic increases along the Milan – Bergamo route;
  • Permanent redistribution of the traffic flows allocated to the LL and DD lines, ensuring that the anticipated increases in traffic are manageable.
acav
250 km/h maximum speed
1,2 km
252,4 mln €

Work progress

Here are the details of the project progress.
  • Design
    Since 2023
  • Permits
    Since 2025
  • Tenders
    -
  • Start of work
    -
  • Activation
    -

ADDA SHUNTING YARD OVERPASS

Progress status: PERMITS