Lunghezza-Guidonia doubling

Lunghezza-Guidonia doubling

The project involves the doubling of the track between Lunghezza and Guidonia along the Rome–Pescara line over a distance of approximately 10 km, most of which will be built alongside the existing line.

As part of the works to open the first section of the double-track line between Lunghezza and Bagni di Tivoli, the upgrade of the Bagni di Tivoli station has been completed. The station will subsequently be renamed Tivoli Terme.

The next phase involves relocating the Guidonia Montecelio station to Collefiorito, installing noise barriers and removing level crossings along the route.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

The project has received partial public funding, including NRRP funds.

Advantages

  • Increased capacity (from 4 trains per hour in both directions to 10 trains per hour in each direction) with the extension of the metropolitan service from Lunghezza to Guidonia, running every 15 minutes.
  • Improved service regularity and optimised rolling stock management, thanks to the upgrade of station facilities at the new Guidonia site.
  • Improved accessibility thanks to road works, the removal of level crossings and the construction of park-and-ride facilities in Guidonia and Bagni di Tivoli.
  • Reduced journey times.
140 km/h maximum speed
10 total kilometres
355 mln € in investments

Work progress status

  • Design
    Since 2008
  • Permits
    Since 2014
  • Tenders
    Since 2021
  • Start of work
    Since 2022
  • End of work
    Since 2025

Doubling Lunghezza - Bagni di Tivoli - Phase 2 Doubling Lunghezza - Bagni di Tivoli (civil works and technologies)

Stages of progression: WORKS 

  • Design end date: 2008*
  • End date of the authorisation process: 2014*
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2025
  • Activation date: 2025

*It should be noted that over the years, there have been contractual rescissions that have distended and reshaped the operations.

Guidonia Collefiorito railway station - Phase 3 Guidonia Collefiorito railway station

Stages of progression: WORKS 

  • Design end date: 2008*
  • End date of the authorisation process: 2014*
  • Date of tender publication: 2021
  • Start date of executive design and implementation: 2022
  • Work end date: 2025
  • Activation date: 2025

*It should be noted that over the years, there have been contractual rescissions that have distended and reshaped the operations.

Bagni di Tivoli - Guidonia - Phase 4 and 5 (Bagni di Tivoli - Guidonia)

Stages of progression: DESIGN

  • Design end date: 2024
  • End date of the authorisation process: 2025