Lecco - Tirano

Lecco - Tirano

The project is part of the Winter Olympic and Paralympic Games Milano Cortina 2026 renovation programme, which includes modifications to the stations and works aimed at eliminating 12 level crossings on the Lecco - Tirano line, as well as on the Colico - Sondrio and Sondrio - Tirano sections along the Stelvio State Road SS38.

Specific works to upgrade the infrastructure focused on improving the efficiency of the junctions at Mandello, Lierna, Ardenno, S. Pietro Berbenno, Colico and Tirano. In addition to these facilities, further works carried out under the agreement on the development and upgrading of the Valtellina and Valchiavenna lines have been completed in Bellano, Ponte in Valtellina and Dubino. In addition to modifications to the station tracks, the works also included extensive accessibility improvements, including the construction of underpasses, new platforms and the optimisation of access routes to the stations.

Aldo Isi was appointed Extraordinary Government Commissioner for the completion of the works.

The advantages

  • Improved flow and safety of traffic by removing level crossings.
  • Overall improvement in traffic flow and possibility of standardising existing services.
135 km/h maximum speed
105 total km
66 mln € of investments

Work progress

Here are the details of the work progress for the Lecco-Tirano line on the Colico - Sondrio and Sondrio - Tirano sections, along on the Stelvio State Road SS38:
  • Design
    Since 2021
  • Permits
    Since 2022
  • Tenders
    Since 2023
  • Start of work
    Since 2024
  • End of work
    Dec 2025

Progress stage:

  • Design end date: from 2021
  • Authorization process end date: from 2022
  • Tender publication date: from 2023
  • Executive design and construction start date: from 2024
  • Completion date: December 2025