Lamezia Terme-Catanzaro Lido-Dorsale Jonica

Lamezia Terme-Catanzaro Lido-Dorsale Jonica

The project involves upgrading the infrastructure through works to improve journey times along the section between Sibari and Melito di Porto Salvo, and the electrification of the sections between Lamezia Terme - Catanzaro Lido and Sibari - Crotone - Catanzaro Lido. The planned works will improve the network’s performance and facilitate connections to and from the Tyrrhenian coast.

The project has received partial public funding, including NRRP funds.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

Advantages

  • The works will make it possible to strengthen the links between the Ionian and Tyrrhenian lines and improve access to Lamezia Terme.
  • Creation of the infrastructure necessary to rethink the local public transport service model through electrification of the entire route between Sibari, Catanzaro Lido and Lamezia Terme Centrale.
  • Restored journey times along the Sibari–Catanzaro Lido and Lamezia–Catanzaro Lido routes.
150 km/h maximum speed
215 total kilometres
438 mln € in investments

Work progress status

  • Design
    Since 2022
  • Permits
    Since 2023
  • Awarding tenders
    Since 2023
  • Start of work
    Since 2024
  • End of work
    2026

Lamezia Terme - Catanzaro Lido dorsale Jonica - Lamezia Terme - Catanzaro Lido dorsale Jonica

Stages of progression: TENDERS

  • Design end date: 2022
  • Activation Date: june 2026
  • Date of tender publication: 2023