New Ferrandina - Matera La Martella line

New Ferrandina - Matera La Martella line

The aim of the project is to connect the city of Matera to the national railway infrastructure by means of a 20 km single-track electrified line, connecting to the current third track at the Ferrandina station, on the Potenza-Metaponto line.

The Matera La Martella station will be served by both a direct connection to the Ferrandina station and a connection to the north.

The project has received partial public funding, including NRRP funds.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

Advantages

  • The main objective of the project is to provide the city of Matera with a connection to the national rail network with the possibility of establishing long-distance services to Rome and local public transport services to Potenza and Taranto.
  • Improved accessibility for passengers with reduced mobility: the new Matera La Martella station will comply with current TSI PRM standards in order to ensure that the rail service is also accessible to passengers with reduced mobility
  • Improved management of station spaces: as part of the new Matera La Martella station project, plans include the redevelopment of the area outside the passenger terminal and the construction of a park-and-ride facility
120 km/h maximum speed
20 total kilometres
525 mln € in investments

Work progress status

  • Design
    2019
  • Permits
    2022
  • Tenders
    2022
  • Start of work
    2023
  • End of work
    2026

Ferrandina - Matera La Martella - Ferrandina - Matera La Martella

Stages of progression: WORKS 

  • Design end date: 2019
  • End date of the authorisation process: 2022
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Work end date: 2026
  • Activation date: December 2026