Expansion of the Salerno-Reggio Calabria railway line

Expansion of the Salerno-Reggio Calabria railway line

The project involves the construction of a new High-speed railway line along the Salerno–Reggio Calabria route, which is a strategic passenger and freight corridor linking the north and south of the country.

Plans also include the construction of several stops along the new line and the doubling of the track for the Paola–Cosenza section via the new Santomarco tunnel, with a view to upgrading the freight route to the Port of Gioia Tauro. The works will ensure greater accessibility to the rail network and the opportunity to develop new passenger services along the north-south axis of the peninsula, which will also benefit connections to and from Sicily.

The entire route from Salerno to Reggio Calabria has been divided into functional sections. Given the scale and cost of the entire project, the study identified possible intermediate timeframes, prioritising certain sections of the project that would deliver the greatest benefits.

In relation to the priority scenario, the project is funded, including through NRRP funds

Aldo Isi was appointed Extraordinary Government Commissioner for the completion of the works.

Advantages

  • The completion of the first operational section between Battipaglia and Romagnano, scheduled for 2026, will reduce journey times by around 20 minutes along the Battipaglia–Potenza route, in conjunction with the planned works on the Battipaglia–Taranto line.
  • Once the entire project is complete, the journey time between Rome and Reggio Calabria will be reduced by up to 4 hours depending on the operating schedule.
  • The new infrastructure will therefore enable the development of new passenger services along the north-south axis of the peninsula, which will also benefit connections to and from Sicily.
  • The infrastructure will enable an increase in freight traffic to the port of Gioia Tauro.
acav
2-300 km/h maximum speed
220 total kilometres
17,487 mld € in investments

Work progress status

  • Design
    Since 2021
  • Permits
    Since 2022
  • Tenders
    Since 2022
  • Start of work
    Since 2023
  • End of work
    Since 2026

Battipaglia - Romagnano - Lot 1a Battipaglia - Romagnano

Stages of progression: WORKS

  • Design end date: 2021
  • Date of tender publication: 2022
  • Start date of executive design and implementation: 2023
  • Activation Date: december 2026

Romagnano - Buonabitacolo - Lot 1b Romagnano - Buonabitacolo

Stages of progression: PERMITS

  • Design end date: 2025
  • End date of the authorisation process: 2025
  • Date of tender publication: 2025
  • Start date of executive design and implementation: 2026
  • Work end date: 2029
  • Activation date: 2029

Buonabitacolo - Praja - Lot 1b Buonabitacolo - Praja

Stages of progression: PERMITS

  • Design end date: 2025
  • Activation date: 2025

Praja Paola - Lot 2 Praja Paola

Stages of progression: DESIGN

  • The DOCFAP has been developed with the Public Debate expected to start between 2025 and 2026.

Doubling of the Santomarco tunnel - Doubling of the Santomarco tunnel (Paola - Cosenza section)

Stages of progression: NEGOTIABLE ACTIVITY

  • Design end date: 2024
  • End date of the authorisation process: 2024
  • Date of tender publication: 2024
  • Start date of executive design and implementation: 2025
  • Work end date: 2032
  • Activation date: 2032

Lots to completion - Lots to completion

Stages of progression: DESIGN

  • The DOCFAP has been developed with the Public Debate expected to start between 2025 and 2026.