Doubling Codogno-Cremona-Mantova

Doubling Codogno-Cremona-Mantova

The project involves the doubling of the Codogno–Cremona–Mantua section in phases.

The first phase involves the doubling of the Piadena–Mantua section, covering a total length of approximately 34 km, whilst the second phase involves the doubling of the Codogno – Piadena section, covering approximately 50 km.

The first phase of the project involves widening the section between Piadena and Mantua, with the work divided into two distinct sub-phases. The first involves the doubling of the Piadena–Bozzolo section, including improvements to the line’s performance, the removal of level crossings, and work to extend the tracks to a length of 750 m at the Marcaria and Bozzolo stations. The second involves the doubling of the track from Bozzolo to Mantua.

The second phase of the overall project, on the other hand, involves the doubling of the single-track sections between Cremona and Piadena and between Codogno and Cava Tigozzi.

The project has received partial public funding, including through NRRP funds, and work is currently underway on track doubling and to remove level crossings as part of the first phase.

“With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.”

Advantages

  • potential increase in the permitted capacity on the line from the current 4 trains per hour to 10 trains per hour in both directions;
  • improved service regularity and safety by removing level crossings;
  • upgraded infrastructure to accommodate freight trains up to 740 metres in length, thereby increasing rail freight capacity;
  • a potential reduction in journey times.
160 km/h maximum speed
84 total kilometres
2,150 mld € in investments

Work progress status

  • Design
    Since 2020
  • Permits
    Since 2022
  • Tenders
    Since 2022
  • Start of work
    Since 2023
  • End of work
    Since 2026

Piadena-Mantova - Doubling of Piadena-Mantova

Stages of progression: WORKS

  • Design end date: 2020
  • End date of the authorisation process:2022
  • Date of tender publication: 2023 
  • Start date of executive design and implementation: 2023
  • Work end date: 2026 
  • Activation date: 2026

 

Cremona-Codogno-Piadena - Doubling of Cremona-Codogno-Piadena

Stages of progression: DESIGN