Doubling and electrification of the Empoli-Siena Railway

Doubling and electrification of the Empoli-Siena Railway

The Empoli–Siena upgrade project includes the electrification of the entire section and the doubling of the track between Empoli and Granaiolo over a distance of approximately 10 km, running parallel to the existing track.

With regard to the section where the line is being doubled, plans also include the removal of all level crossings along the line, the installation of new train control systems, and improvements to accessibility at the Ponte a Elsa station.

 The interventions will lead to increased metropolitan services and a higher operating speed on the Florence-Siena connection.

The Empoli - Siena project has received partial public funding.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

Advantages

  • Increased line capacity (from 4 trains per hour in both directions to 10 trains per hour on the sections where the track is being doubled).
  • More frequent services between Empoli and Siena.
  • Environmental sustainability.
120 km/h maximum speed
10 total kilometres
354 mln € in investments

Work progress status

  • Design
    Since 2018
  • Permits
    Since 2022
  • Tenders
    Dal 2022
  • Start of work
    Dal 2023
  • End of work
    Since 2027

Doubling of Empoli-Granaiolo - Doubling of Empoli-Granaiolo

Stages of progression: TENDERS 

  • Design end date: 2018
  • End date of the authorisation process: 2022
  • Date of tender publication:2022
  • Start date of executive design and implementation: 2023
  • Work end date: 2027
  • Activation Date: 2029

Empoli-Siena electrification - Empoli-Siena electrification

Stages of progression: PERMITS

  • Design end date: 2019
  • End date of the authorisation process: 2025
  • Date of tender publication:2025
  • Start date of executive design and implementation: 2026
  • Work end date: 2028
  • Activation Date: 2029