Connection Project to the Messina Strait Bridge

Connection Project to the Messina Strait Bridge

The project concerns the construction works required to build the rail link between the Messina Strait Bridge infrastructure – falling under the remit of Stretto di Messina S.p.A. – and the existing railway lines on both sides of the Strait, in Calabria and Sicily.

Specifically, the following are defined:

  • On Calabria’s side: Connection to the existing Battipaglia–Reggio Calabria railway line, with new branches reaching the Villa San Giovanni and Reggio Calabria stations, and a new variant to the existing line, where these new branches will be connected to.
  • On Sicily’s side: Connection to the existing Messina–Catania railway line, with a branch towards Messina, achieved through a flush junction in Gazzi, and another branch towards Catania, achieved by building a curve on the new layout of the Contesse railway yard. In addition to connections to the existing rail network, the project provides for the demolition of the first section of the seaside-facing fiddle yard at the Messina Centrale station. A further project, called “Construction of the New Messina Gazzi Station”, is also planned and will be the subject of a future design study.

With effect from 12 March 2026, the date on which Decree-Law 32 (published in the Official Journal 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI S.p.A. has been appointed Extraordinary Commissioner.

Advantages

Shore connections are required for the Messina Strait Bridge railway operation. Journey times will be reduced by establishing a urban service in the Strait area.
100 km/h maximum speed
7.3 total km
1.7 bn € of investements

Work progress

Here are the details on the progress of the project “Connection Project to the Messina Strait Bridge”:
  • Design
    from 2024
  • Permits
    from 2025
  • Tenders
  • Start of work
  • Activation

Connection Project to the Messina Strait Bridge - Sicily side - Connection Project to the Messina Strait Bridge - Sicily side

Stages of progression: PERMITS

  • Design end date: 2026
  • End date of the authorisation process: 2026
  • Date of tender publication: 2027
  • Start date of executive design and implementation: 2028
  • Activation date: 2034

Connection Project to the Messina Strait Bridge - Calabria side - Connection Project to the Messina Strait Bridge - Calabria side

Stages of progression: PERMITS

  • Design end date: 2026
  • End date of the authorisation process: 2026
  • Date of tender publication: 2027
  • Start date of executive design and implementation: 2028
  • Activation date: 2034