Ciampino-Capannelle track-quadrupling

Ciampino-Capannelle track-quadrupling

The project involves a four-track expansion between Capannelle and Ciampino, with an extension of approximately 6 km alongside the existing line. Plans also include an upgrade to the Ciampino station and the Capannelle stop, with improvements to the stop’s services (park-and-ride) as well as to the surrounding road network through the upgrading of the underpass on Via di Capannelle.

The Ciampino–Capannelle project has received partial public funding.

“With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.”

Advantages

  • Increased frequency of services along the RM Termini–Ciampino line.
  • Improved service regularity.
  • Improved accessibility for customers.
  • Increase in capacity from 10 trains per hour to 20 trains per hour and improved service regularity.
  • Specialisation of services.
150 km/h maximum speed
6 total kilometres
255 mln € in investments

Work progress status

Ciampino-Capannelle and General Regulatory Plan for the Rome branch line - Quadrupling of the Ciampino-Capannelle and General Regulatory Plan for the Rome branch line
  • Design
    2021
  • Permits
    2025
  • Tenders
    .
  • Start of work
    .
  • End of work
    Since 2026

Ciampino-Capannelle and General Regulatory Plan for the Rome branch line - Quadrupling of the Ciampino-Capannelle and General Regulatory Plan for the Rome branch line

Stages of progression: PERMITS

  • Design end date: 2021
  • End date of the authorisation process: 2025