Augusta Port and Bypass

Augusta Port and Bypass

The works involve the implementation of two projects in the Augusta area. The first project concerns the construction of a variant for the Messina–Syracuse line around the town centre of Augusta. Plans are in place to build a new station located outside the town centre, in a new development area.

The second phase forms part of the expansion project for the Augusta Commercial Port and involves the construction of a railway link connecting the new railway yard to the main rail network.

The project is fully funded, including through NRRP funds.

“With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.”

Advantages

  • The Augusta variant makes it possible to eliminate interference between the national rail network and the urban fabric of the city.
  • Increased rail-ship intermodality and development of freight transport with performance characteristics in line with TEN-T network standards.
90 km/h maximum speed
4.4 total kilometres
281 mln € in investments

Work progress status

  • Design
    Since 2022
  • Permits
    Since 2024
  • Tenders
    Since 2024
  • Start of work
    Since 2024
  • End of work
    Since 2026

Augusta rail bypass - Augusta rail bypass on the Catania-Siracusa railway line

Stages of progression: WORKS

  • Design end date: 2022
  • End date of the authorisation process: 2024
  • Date of tender publication: 2024
  • Start date of executive design and implementation: 2024
  • Work end date: 2026 
  • Activation Date: 2026

Port of Augusta - Rail link in the Port of Augusta

Stages of progression: DESIGN

  • Design end date: 2023
  • End date of the authorisation process: 2024
  • Date of tender publication: 2024
  • Start date of executive design and implementation: 2025
  • Work end date: 2026 
  • Activation Date: 2026