FS Cantieri Parlanti: Napoli - Bari HS/HC line: excavation of the Rocchetta Tunnel completed

The longest tunnel on the Apice–Hirpinia section

Naples, 5 May 2026

Work continues on the new Naples–Bari high-speed/high-capacity railway line: the excavation of the Rocchetta Tunnel, the longest of the three tunnels planned along the Apice–Hirpinia section, has been completed.

Located between the provinces of Avellino and Benevento, the tunnel is 6.5 kilometres long and is one of the most challenging projects in the contract, built in an area that is particularly complex from a structural and topographical point of view. The tunnelling work was carried out by the “Futura” TBM which worked non-stop 24 hours a day, seven days a week, completing the tunnel in 18 months at an average rate of 16 metres per day, with peaks of over 29 metres, and installing over 32,500 precast segments to form the final lining of the tunnel.

The contract for the Rocchetta Tunnel works was awarded to Webuild by Rete Ferroviaria Italiana, with FS Engineering acting as project manager.

Rocchetta is the second tunnel to be completed on this section, following the Grottaminarda Tunnel. Excavation of the Melito Tunnel, which is approximately 4.4 kilometres long, is scheduled to begin by the summer.

The entire Naples–Bari high-speed railway line, which forms part of the TEN-T Scandinavia–Mediterranean European rail corridor and is also funded through PNRR funds, comprises 145 kilometres of track, 15 tunnels, 25 viaducts and 20 stations and stops. These activities form part of the FS Italiane Group’s “Cantieri Parlanti” project, an initiative designed to show the public the progress of major infrastructure projects and the expected benefits for the local areas involved.

Work is progressing on several fronts along the entire Naples–Bari route. The Cancello–Frasso Telesino section, spanning approximately 16.5 kilometres (4 kilometres of which are in tunnels), has been implemented in two phases: as a single-track line in September 2025 and as a double-track line in February 2026. Work has been completed on the 15.6-kilometre-long Naples–Cancello section, where preparations are currently underway for the line to begin operating by the summer. Work is also nearing completion on the Frasso–Telese and Telese–Vitulano track -doubling projects, which have already seen the implementation of a series of subsequent phases and the completion of 7 of the 8 planned tunnels.