Completion of the track-doubling for the Genoa-Ventimiglia line

Completion of the track-doubling for the Genoa-Ventimiglia line

The project involves the construction of a second track, following a different route from the one currently in use, on the section between Andora and Finale Ligure, covering a distance of approximately 32 km, 25 km of which will be in tunnels. This will enable the completion of the doubling of the Genoa – Ventimiglia international line.

The project includes the construction of the new Albenga station and of stops at Alassio (in a tunnel), Borghetto-Ceriale-Loano and Pietra Ligure. With the new infrastructure and the decommissioning of the existing line, 14 level crossings will be removed and the current facilities at Laigueglia, Alassio, Albenga, Ceriale, Borghetto S. Spirito, Pietra Ligure and Borgio Verezzi will be decommissioned.

The project is currently at the design stage, and the full work schedule will only be finalised once full funding for the construction phase has been secured. Funding for the project is currently limited to the design phase only.

With effect from 12 March 2026, the date on which Decree-Law No. 36 (published in the Official Gazette No. 58 of 11 March 2026) came into force, in accordance with Article 5 of that decree, the Chief Executive Officer of RFI SpA has taken over from the previously appointed Extraordinary Commissioners.

Advantages

  • Increased capacity of the double-track section, thereby enabling an increase in the volume of rail freight and passenger services;
  • Improved safety levels by removing the level crossings following the closure of the existing line;
  • No risks to the infrastructure currently exposed to marine erosion;
  • Potential reduction in journey times.
acav
200 km/h maximum speed
32 total kilometres
2,576 mld € in investments

Work progress status

  • Design
    2021
  • Permits
    2025
  • Tenders
    .
  • Start of work
    .
  • End of work
    Since 2029

Andora-Finale - Doubling Andora-Finale

Stages of progression: PERMITS

  • Design end date: 2021
  • Activation Date: 2029